Police Facility,
Tuesday, January 27, 2009, 4:00 p.m.
CALL TO ORDER
Mayor
PLEDGE OF
ALLEGIANCE
The mayor led in the Pledge of Allegiance.
ROLL CALL
PRESENT: Councilmembers
CALL TO THE PUBLIC
There were no
requests to address the council.
PUBLIC HEARING: DISCUSSION
AND DIRECTION RE: PRESENTATION ON WATER RATE, IMPACT AND SERVICE FEE UPDATE
Ms. Gayle
Whittle, Finance Director, advised that Red Oak Consulting was in attendance to
present several revised scenarios based on council’s instructions at the
September 30, 2008, meeting. Ms. Whittle said the council communication also
included a proposed timeline to move forward with adopting impact fees and
water rates. She added that this presentation would focus on the impact fee
portion because the rate plan and proposed rate designs are not ready for
presentation at this time.
Ms. Whittle gave
the following background information:
On September 24, 2002, the council adopted a three-year rate plan for
the water rates and implemented a 10 percent increase on October 24, 2002; a 10
percent increase on July 1, 2003; another increase on July 1, 2004; and there
have not been any water rate changes since July 1, 2004.
In September 2003, Red Oak Consulting completed a water financial plan
and rate study, and presented impact fees to the council at that time. Red Oak
modeled the water rates from the water rates that the council had already
adopted, so no new water rates were proposed at that time.
Ms. Whittle was hired on March 4, 2005, and at that time,
recommendations were already in process for implementation of a water system
development fee and a water resources development fee.
Those fees were adopted by the council in June 2005, effective
September 13, 2005.
On December 13, 2005, the council rescinded the impact fees and at that
same meeting, the council awarded a contract to Carollo Engineers to begin a
Water Master Plan update.
On March 27, 2007, the council authorized a loan agreement with the
Water Infrastructure Finance Authority (WIFA) to borrow up to $7.5 million, but
actually borrowed $5.7 million, and pledged that the city would have 1.2 times
debt service coverage for revenues, and would also maintain a 20 percent cash
reserve.
On November 13, 2007, the council adopted the Water Master Plan update.
On December 3, 2007, staff advertised for a Request for Proposal (RFP)
to do a Water Rate Impact and Service Fee study.
On February 26, 2008, that contract was awarded to Red Oak Consulting. Since
that time, city staff has been working with information derived from the Water
Master Plan to come up with a Community Investment Plan (CIP), and Red Oak has
worked on several different scenarios.
Red Oak came before the council in September 2008, and at that time,
the council asked for Red Oak to bring back some revised scenarios.
Ms. Whittle
explained that this item is not something that suddenly appeared on the horizon
because of the depressed revenues, but has actually been a work in progress
since 2005, trying to complete the Water Master Plan, along with the rate
study.
Ms. Pat
Walker and Mr. Kevin Burnett, both from Red Oak Consulting, were in attendance
to give a presentation. Ms. Walker gave the presentation objectives:
Provide on overview of the study for the benefit of the new councilmembers.
Update city council on study progress.
Receive direction in regard to the capital plan and which financial
plan the council would like to see move forward to the next council meeting.
Ms. Walker
said that a comprehensive rate study begins with the financial planning
component. It begins with the Master Plan and consideration the projects needed
to not only be able to provide water and sewer service to existing customers,
but for the future customers. Once that is done, and then the CIP is built by
looking at the components that include Operations and Maintenance (O&M),
sources and uses of funds, impact fees, debt service, reserves, and the
different financing tools that can be used.
Ms. Walker
stated that the city is in the financial planning stage, and what that means is
that the city will look at what revenues will be taken in and what the expenses
the city has, and if the revenues are less than the expenses, then that is the
necessary revenue increase. She clarified that the rate increases have not been
designed yet, so the city would only be looking at what its system needs in
order to recover the revenues to pay the bills. The cost of service would then
be analyzed to determine whatever percentage is needed to serve a residential
or commercial customer, and then by using the rate design and rate structures,
the amount needed to recover the costs for each of the classes could be
determined. She said that in other words, the city would look at the various
pricing objectives such as what type of rate structure should be built to collect
the water and sewer fees. Would the city want conservation, revenue stability,
or both?
Ms. Walker
said that for financial planning, WIFA requires two major criteria: cash
reserve ratio and debt service coverage. The cash reserve ratio is 20 percent, or 73 days of annual O&M
expense, and since it is required by WIFA, it is a driver in the study and the
financial plan. The debt service coverage is 1.2 times the annual debt service,
which is calculated by dividing the combined net revenues by the annual debt
service payment.
The following
assumptions were used in the study and are very important because they dictate the
results of the study:
Growth
0.5% beginning in FY 2008-09,
0.75% in FY 2011-12,
1% in FY 2013-14, and
1.5% in FY 2015-16.
Other assumptions
O&M expenses are projected to increase at
3 percent per year with the exception of personnel costs, which when adding in
salaries and benefits, it will usually increase at 5 percent per year.
CIP is projected to increase at 4 percent per
year.
Revenue increases are projected to be
effective July 1, 2009, and April 1, thereafter.
Rate increases assume conservation and will
not necessarily equate to an equal revenue increase.
Ms. Walker
said the projected CIP have all been identified in the Master Plan. She noted
that when she reported to the city council in October 2008, the CIP presented
to council was $157 million. She said the council directed city staff to relook
at the CIP as Red Oak would run different scenarios. She noted that the city
staff identified essential projects that needed to be done that amounted to
$107 million. By the way, the study period is until 2018/19, which is 10 years
from this fiscal year. She advised that the Core/ Essential & Delay CIP
projects are those projects that Public Works Director
Ms. Walker
presented a graph showing the initial and revised compared-inflated amounts of
the CIP for FY 08/09 to FY 18/19. She said she had mentioned that one of the
pieces of the financial plan is how much the city will collect in impact fees
in order to fund those growth-related projects, because growth-related projects
are included in that $79 million. In order to do that, different methodologies
can be used such as buy-in, hybrid, or a planned-based approach which looks at
future growth. She said the council consensus was for the buy-in approach,
which looks at all the city’s assets at today’s dollars and projecting them out
in the future, and then consider which growth that will serve. Ms. Walker
advised that the fee would be based on a $3,894 buy-in approach in conjunction
with the current water resource fee of $660 which would increase to $835.
Ms. Walker
also advised that by using the Essential & Delay CIP of the full $107
million, the impact fee would be even higher at $4,407 per residential
household.
Ms. Walker
compared the current residential development fees with other
Ms. Walker
proceeded to discuss the various scenarios for the financial plan. She said
there is a lot of discussion regarding percentages, but she advised the council
to remember where
Ms. Walker
explained the details of a “No CIP Scenario.”
No CIP for the first three years, Core/Essential
CIP at $73 million. The CIP amount is reduced from $79 million to $73 million
because when projects are pushed out, they go beyond the study period, and therefore
the amount drops. This scenario assumes that impact fees will remain the same with
no CIP from FY 09/10 through FY 12/13.
Monthly bill increases from $23.74 today to
$51.46 in FY 18/19.
$61.0 million in bonds are issued.
CIP is deferred for three years. A 12 percent
rate increase would still be needed.
Revenue increases are needed to meet cash
reserve ratio and minimize issuance of non-growth capital related debt.
Plan meets revenue requirements and cash
reserve ratio on an Operations and Total Fund basis.
Fully funds capital improvements plan of $82
million (which is inflated over that time period).
Ms. Whittle
said she asked Red Oak Consulting to present this scenario because this is
unrealistic in that there must be some CIP to replace water lines in
conjunction with the sewer project. She said money was borrowed for that, but
the city needs to raise revenue in order to meet its financial ratio
calculations. She noted that some of the booster stations cannot wait for three
years to be serviced, and they are very expensive to repair. She also noted
that since the Irrigation and Drainage District (IDD) will not have any money,
the money would have to come out of the General Fund Contingency.
Ms. Walker
also noted that with no CIP, the rate increase would be at 12 percent, but the
rates have not increased since December 2004, yet with an inflationary rate of
3 percent to 4 percent, the increase would need to be at approximately 12
percent to 16 percent, just for all the different items needed for the
operation and maintenance, salaries, etc., with the Enterprise System.
Ms. Walker
presented the following scenarios:
Scenario 1:
Essential & Delay the CIP ($107 million CIP). It assumes the current impact
fees with no increase:
Monthly bill increases from $23.74 to $31.10 in FY 09/10 for 13 ccfs and
to $64.61 for 13 ccfs in FY 18/19.
$94.0 million in bonds issued.
Revenue increases are needed to meet cash reserve ratio and minimize
issuance of non-growth capital related debt.
Plan meets revenue requirements and cash reserve ratio on an Operations
and Total Fund basis.
Fully funds capital improvements plan of $125 million (based on 4
percent inflation).
Scenario 2:
Essential & Delay the CIP ($107 million CIP). Rates, current impact fees
based on the current water resource fee of $660 assessed outside the IDD, and
continued IDD tax beginning in FY 13/14:
Monthly bill increases from $23.74 to $31.10
in FY 09/10 for 13 ccfs and to $60.24 for 13 ccfs in FY 18/19.
$94.0 million in bonds issued.
Revenue increases are needed to meet cash
reserve ratio and minimize issuance of non-growth capital related debt.
Continued IDD tax helps to offset reliance on
rate revenue in later years of plan.
Plan meets revenue requirements and cash
reserve ratio on an Operations and Total Fund basis.
Funds capital improvements plan of $125
million (inflated).
Scenario 3: Essential & Delay the CIP ($107 million CIP). Based on the current water
resource fee of $660 assessed outside the IDD.
Monthly bill increases from $23.74 to $30.39 in FY 09/10 for 13
ccfs and to $57.48 for 13 ccfs in FY
18/19 by updating impact fees.
$94.5 million in bonds issued.
Revenue increases are needed to meet cash
reserve ratio and minimize issuance of non-growth capital related debt.
Plan meets revenue requirements and cash
reserve ratio on an Operations and Total Fund basis.
Funds capital improvements plan of $125
million (inflated).
Scenario 4:
Core/Essential CIP, but it is delaying some of the projects ($79 million CIP).
Based on the current water resource fee of $660 assessed outside the IDD.
By updating the impact fees, the monthly bill increases from $23.74 to
$30.62 in FY 09/10 for 13 ccfs and $53.94 for 13 ccfs in FY 18/19.
$73.0 million in bonds issued.
Revenue increases are needed to meet cash reserve ratio and minimize
issuance of non-growth capital related debt.
Plan meets revenue requirements and cash reserve ratio on an Operations
and Total fund basis.
Fully funds capital improvements plan of $90 million (inflated).
Scenario 5:
Core/Essential CIP ($79 million CIP). Rates, current impact fees, and continued
IDD tax beginning in FY 13/14.
Monthly bill increases from $23.74 to $30.62 in FY 09/10 for 13 ccfs
and $50.18 for 13 ccfs in FY 18/19.
$73.0 million in bonds issued.
Revenue increases are needed to meet cash reserve ratio and minimize
issuance of non-growth capital related debt.
Continued IDD tax helps to offset reliance on rate revenue in later
years of plan.
Plan meets revenue requirements and cash reserve ratio on an Operations
and Total fund basis.
Funds capital improvements plan of $90 million (inflated).
Scenario 6:
Core/Essential CIP ($79 million CIP). This is the updated impact fee buy-in
approach.
Monthly bill increases from $23.74 to $30.62 in FY 09/10 for 13 ccfs
and $52.41 for 13 ccfs in FY 18/19.
$73.0 million in bonds issued.
Revenue increases are needed to meet cash reserve ratio and minimize
issuance of non-growth capital related debt.
Plan meets revenue requirements and cash reserve ratio on an Operations
and Total fund basis.
Funds capital improvements plan of 490 million (inflated).
Ms. Walker reviewed
the scenario comparisons, and noted the various differences with rate increases:
|
|
No CIP |
1 |
2 |
3 |
4 |
5 |
6 |
|
Description |
Rates, Cur impact fee, $79 CIP, No CIP first 3 yrs |
Rates, Cur impact fee, $107 CIP |
Rates, Cur impact fee, IDD, $107 CIP |
Rates, Higher impact fee, $107 CIP |
Rates, Cur impact fee, $79 CIP |
Rates, Cur impact fee, IDD, $79 CIP |
Rates, Higher impact fee, $79 CIP |
|
Rate Increases |
|||||||
|
FY 08-09 |
0% |
0% |
0% |
0% |
0% |
0% |
0% |
|
FY 09-10 |
12% |
31% |
31% |
28% |
29% |
29% |
29% |
|
FY 10-11 |
12% |
10% |
10% |
10% |
10% |
9% |
10% |
|
FY 11-12 |
12% |
10% |
10% |
10% |
9% |
8% |
9% |
|
FY 12-13 |
9% |
12% |
8% |
12% |
9% |
6% |
9% |
|
FY 13-14 |
9% |
12% |
9% |
10% |
9% |
6% |
9% |
Ms. Walker
advised that in the following chart, $23.74 is the current rate, $31.10 in FY
09/10, and $47.20 in FY 13/14. She noted that with a higher impact fee and no
IDD tax, the rate increases to $43.63 in FY 13/14.
|
|
No CIP |
1 |
2 |
3 |
4 |
5 |
6 |
|
(1) Description |
Rates, Cur IF, $79 CIP, No CIP First 3 yrs |
Rates, Cur IF, $107 CIP |
Rates, Cur IF, IDD, $107 CIP |
Rates, Higher IF, $107 CIP |
Rates, Cur IF, $79 CIP |
Rates, Cur IF, IDD, $79 CIP |
Rates, Higher IF, $79 CIP |
|
Bill Today |
$23.74 |
$23.74 |
$23.74 |
$23.74 |
$23.74 |
$23.74 |
$23.74 |
|
Bill 09-10 |
$26.59 |
$31.10 |
$31.10 |
$30.39 |
$30.62 |
$30.62 |
$30.62 |
|
Bill 13-14 |
$39.63 |
$47.20 |
$44.30 |
$45.30 |
$43.63 |
$40.51 |
$43.63 |
(1) Assumes 13 ccf monthly water usage
Ms. Walker
said that in comparison to Kingman,
Mayor Nexsen
asked what the differences were between Scenarios 1 and 3. Ms. Walker explained
that Scenario 1 has the current impact fee and Scenario 3 has the increased
impact fee, so it is the timing of growth-related projects as to when it
affects what year. Mayor Nexsen asked why the revenue or the rate increase
would still need to increase to 28 percent versus 31 percent. Ms. Walker said
that was because of the O&M costs and the timing. She said there are a lot
of components in the plan, one of which is the financing, and because the city
does not have the cash up front for the impact fees, the financing is paid part
with cash and part with financing. She further noted that the impact is felt in
the long term by having impact fees because that is cash coming in to pay for
the projects. Mayor Nexsen thought there must be a very small amount of impact
fees being collected. Mr. Burnett commented that the other issue taking place
with the 0.5 percent growth for the next couple of years is that the impact fee
revenue generated on that growth is so small that it does not really have an
impact until it builds up over time.
Mayor Nexsen
asked if the impact fee would be for inside and outside the IDD. Ms. Walker
said that was correct, although a credit of $864 was calculated for inside the
IDD. Ms. Walker clarified that the credit is included in the $2,855 impact fee
in FY 09/10 of Scenario 3. Mayor Nexsen asked why the people inside the IDD
would not also get credit for the excess capacity that is built in, in terms of
water availability, because the city has more water than it needs inside the
IDD. He also noted that the city has already purchased water that allows for
full growth inside the IDD as well as some growth outside the IDD, so since the
city has already paid for the water, then why not have new growth pay a credit and
bring the costs to an even keel. Ms. Walker explained that the methodology used
is the “buy-in” approach, so when new people come to
Mayor Nexsen
said the new people are going to get the benefit of water that the city already
owns, so if there was no such thing as outside the IDD, then the city would not
be buying water today because there would be plenty of water, but since the
city has this extended water service area, there would be an abundant
allocation of water if the city did not grow at all. He said he is struggling
with why the people outside the IDD should not have to give a credit to
everyone inside the IDD for that excess capacity. He said all the people inside
the IDD have already bought 27,000 acre-feet of water, and it is more than
enough to cover everybody inside the IDD. Mr. Clark suggested that the 27,000
acre-feet of water actually represents about three components, and the last
component was the 2,000 acre-feet of
Councilmember
Wedemeyer asked for clarification of whether the city pays for the water or the
rights to the water. Dr. Wilson explained that the city’s contract covers up to
an entitlement of 27,000 acre-feet, and the city does pay for it, but the cost
is only $.25 per acre foot, so there is a nominal fee paid to the federal
government every time the city asks for an annual allocation. He also clarified
that the water allocation is set in the city’s contract and it is not “use-it
or lose it,” because the water will eventually be used.
Dr. Doyle
Wilson advised that the city currently has a water allocation of 27,319
acre-feet, and the city diverted approximately 17,000 acre-feet last year, and
it does not get banked, but is used by the Central Arizona Project (CAP). Mr.
Clark explained that
Councilmember
Barlow asked the statutory requirements were to impose an impact fee. He
thought the only way an impact fee could be implemented was if the fee was for
future growth and future use of whatever the city was charging for. Ms. Whittle
explained that once the projects are determined, then allocate what percentage
of the project is due to growth, and then charge an impact fee for growth for
those projects. She clarified that with the buy-in method, the calculations are
based on what the city currently has. She said the impact fee is not based on
what the city has now plus what it will own in the future. She said the impact
fees will help fund those projects in the future, but the new customers are
buying into a proportional ownership of what the city currently owns, and that
cash will fund what the city intends to build in the future.
Mayor Nexsen
said the current impact fee for water resource is currently $660 and is only
applied to people outside the IDD, and that is to purchase future water, but what
about the fact that the city has enough water for them already, then should
they not pay the city back. Ms. Walker explained that as new people come into
Ms. Walker
asked to address a few of the questions and concerns that were discussed. She
said that according to the state statute, growth is to pay for growth-related
projects or for the impact to services that growth has on a community, and it
does not dictate the methodology used. She said that the methodologies used to
calculate the impact fees that people should pay as a result of the impact of
growth are: 1) the buy-in methodology, which probably would not collect as much
money to pay for the new projects, and there is a balance; 2) the hybrid
methodology, which is based on existing and new growth projects; or, 3) the plan-based
approach, which has higher impact fees because it looks only at new growth
projects in the future.
Ms. Walker
explained that the formula for impact fees is to look at the cost of the water
system, which is based on the assets in today’s dollars divided by the units to
be served today and in the future. She said that also considered is the
population over this time period, and not looking at the full population out,
but instead looking at the 10-year window, which is how the city’s water system
fee is calculated.
Ms. Whittle
said that in this plan, the city is not looking at purchasing additional
allocations of water, and what the water resources fee is being allocated to is
the expansion of the treatment plant and development of new wells. She further stated
that those two projects have a portion that goes to the water resources fee
because water resources are being developed. She said the prior fee, which was
based on the 2003 report, was only looking at purchasing additional water
allocation because the city did not have the level that it has now, and that
there are different components in this study than there were in the prior
study.
Mayor Nexsen
commented that when adding up all the numbers for the sewer and water, and
extending the current police and fire services, the impact fee for inside the
IDD would total approximately $11,000. Mayor Nexsen asked how the impact fee
for a commercial operation fell into this equation. Ms. Walker replied that the
fee was based on meter size, and as the demand on the system increases, so does
the size of the meter, which would result in a higher impact fee.
Mayor Nexsen
opened the public hearing.
Mr. Chuck
Vaughn asked if the impact fees would be recalculated if the city received
money from the stimulus plan, and how many water-related CIP projects were
applied for in the stimulus project, to which Mr. Clark replied that not a
significant amount of water-related projects were listed. Mr. Vaughn said there
were a lot of residents on a fixed income such as Social Security, and he hoped
that the city would try to keep the sewer and water rate increases to a
minimum.
Mayor Nexsen
closed the public hearing.
Councilmember
Barlow asked if the population figures for
Mr. Clark
advised that last summer, the existing water treatment plant reached about 82
percent capacity, and it is not a case of needing to construct a water
treatment plant because of a large amount of people moving to
Councilmember
Wedemeyer asked if builders were informed that it was possible that another
impact fee was coming at some point in time. Mr. Kaffenberger replied that
nothing was sent out specifically, but there have been several occasions where
impact fees were discussed. Ms. Walker advised that part of the Arizona State
Statute requires a Notice of Intent, which also gives 60 days for discussion
before it even comes back to the council for a public hearing. She said that
part of the process was to bring the study forward, put a copy of the study in
the City
Councilmember
Barnes felt that along with the building impact fee for commercial and
residential, the sewer hook-up fee for current and future residents, and a
sewer rate increase of 10 percent for three years which is about 34 percent compounded,
there are also proposed water impact fees, water rate increases, and possible
increased fees for service, and that about makes it impossible for the low
income, fixed income, and jobless citizens in the community to deal with the
situation. He said he does not feel this is the right time to do this.
Mayor Nexsen
said that from a logical standpoint, he considers Scenario 5 to be the most
fair, but with electric rates increasing by 25 percent, sewer rates increasing
34 percent over the next three years, and a small increase to the water rate
because there has not been an increase in five years, the rates will increase
100 percent within 10 years, and the people just cannot afford it. He thought that
if the city receives stimulus money or money from the Colorado River Sewer
Coalition (CRRSCo) efforts, then that could decrease the sewer bill. He said the
utilities need to be looked at as an overall impact, and there is a point where
the people just cannot afford the costs. He felt that the people might be able
to handle an increase of $3 per month, but to ask them to pay more could pose a
hardship. He realizes that from a logical standpoint, the city must pay for
these projects and pay for the replacements and repairs, but city funds are
running out.
Councilmembers
Barnes and Callahan agreed that there are a lot of people that are hurting
right now, and city government, to a degree, needs to think about those people
too. Councilmember Callahan said that the current utility rates are driving
people away because they cannot afford to pay them. He suggested that the costs
for CIP projects might have to come out of the General Fund, and if that is the
case, then maybe that is what has to happen for just a certain period of time.
Ms. Whittle advised that the General Fund has no money, so if there were an
emergency such as a waterline break, the water would continue to run down the
street because the city cannot fix it right away. She also mentioned that in
order for the city to meet its financial obligations to WIFA, there must be a
12 percent increase, and if the city does not keep its financial commitment to
WIFA, they will not give the city another loan, and that impacts the sewer
system, as well as other loans that might be acquired for the water system. She
advised that the council made a commitment that rates would be raised
sufficient to meet those financial ratio criteria.
Councilmember
Wedemeyer asked if there was another way to save money in terms of how the city
delivers the water to the houses. Mr. Chuck Michalski, Water Division Manager,
said that due to the elevations in the city, the cost for pumping water exceeds
most communities of comparable size. He assured the council that when any of
the booster stations have been rebuilt, he has tried to design the best and
most efficient pump station as possible.
Ms. Whittle
advised that the purpose of this meeting is to decide:
1. Does the council want to charge impact fees or not. If the
council wants to choose impact fees, then there are several scenarios to choose
from, and if the council does not, then there are also several scenarios to
choose from.
2. Should the IDD tax continue in FY 13/14 and not be transferred
to wastewater and be kept in the IDD.
3. If there are no impact fees, then should the
rates pay for everything that is needed?
Councilmember
Barlow felt that it does not do any good to have an impact fee if nothing is
going on, which is basically what is happening right now, and if the council
decided to do an impact fee, then it would not have any impact because there is
no building. He said that when he thinks of CIP, he thinks of some large
project, such as the second bridge, but the Core/Essential system CIP 2008
projects on the list are more everyday items. Ms. Whittle explained that the
top portion of the worksheet lists maintenance to the existing system, and then
lists a few items that are growth related. Councilmember Barlow noted that if
an impact fee is imposed, and it does not generate any money, the system will
still have to be maintained. Ms. Whittle agreed and said the costs for these
are covered by the rates. She also noted that the 12 percent increase will not
pay for anything on the CIP list.
Councilmember
Nyberg asked if there was a way to make the rate increases smaller by putting
the CIP off for one year instead of three years, and Ms. Whittle replied that would
only be shifting it over one year.
Mayor Nexsen
asked how many citizens only used 1,300 ccfs or less, and Ms. Walker advised
that 66 percent of the residential customers used that amount of water, and at
that rate, they pay approximately $24 per month. Mayor Nexsen said that
two-thirds of the citizens are obviously the lower water users. He suggested a
solution where the city would charge a flat fee of $3 per person, which is
similar to how Kingman charges its water users, and the fees are used for
replacement of water lines, etc. He added that
Mayor Nexsen
said he has already decided that the impact fees are doing nothing for rates,
so why have them, and instead of going 29 percent, 10 percent, 9 percent, and 9
percent, his solution will raise more than 12 percent, plus those who choose
not to conserve and who use more water will pay a higher rate. He also said
that he did not want Red Oak Consulting to come back with scenarios to choose
from, but he would rather explore some other ways to get to a better answer.
Ms. Whittle
asked for a consensus from the council whether or not to have impact fees, and
if the council chooses no impact fees, then their scenarios are restricted to
Scenarios 1, 2, 4, and 5. She said Scenarios 3 and 6 are out of the picture,
and so they will not do any more on the financial plan with regard to impact
fees, and that means that all revenue has to be generated by rates. Mayor
Nexsen said that looking at Scenarios 5 and 6, Scenario 6 has an impact fee,
but the amount being generated by rates is virtually the same, so forget impact
fees, and continue to retain the IDD tax.
Mayor Nexsen
commented that most of what is going to be done has nothing to do with growth –
it has to be dealing with replacement of existing lines. Ms. Whittle noted that
the most expensive project on the list, the water treatment expansion, does
have to do with growth, because additional people coming into the city require
that treatment capacity. She also noted that the city has water allocation
capacity, but not treatment capacity for that entire allocation. Mayor Nexsen
recognized that the treatment capacity is currently at 82 percent, but he felt
confident that if the city starts charging more for the high water users, the
available capacity of the treatment plant will be increased, and therefore, the
expansion will not be necessary.
Councilmember
Barnes suggested charging all water users $.15 per day as a fixed amount on the
water bill. Ms. Whittle said that Red Oak Consulting will incorporate these
suggestions into proposed alternative rate designs for consideration by the
council. Ms. Whittle said it appears to be the consensus of the council not to go
forward with impact fees, which means that the financial plan will be funded
with rates. It was also suggested by the council that the impact fees would
only apply to areas outside the IDD. Mayor Nexsen clarified that the impact fees
currently in place inside the IDD pertain to police, fire, and general
government, and so those would not change. He said the question is whether or
not to add a water impact fee to the current fees in the IDD. He also explained
that there is currently a water resource impact fee in place outside the IDD,
and he is not suggesting that change either.
Councilmember
Barnes noted that the city charges its customers for the cost of the water
meter and its installation, plus the $660 impact fee.
Ms. Whittle
clarified the council consensus:
1. Move
forward with the $79 million plan.
2. Move
forward with keeping the IDD tax inside the IDD at the end of the wastewater
program.
She said that
the council’s plan is basically Scenario 5, and Red Oak Consulting will design
the rate structure to meet the council goals that have been expressed.
ADJOURN
The meeting
adjourned at 5:41 p.m.
______________________________________
Carla
Simendich, City