HELP CENTER
ANNUAL STREET SEALING PROGRAM

As part of the annual effort to keep our roads in good condition, Lake Havasu City is starting its annual pavement preservation efforts on Monday, April 15, which is expected to last four weeks. Approximately 650,000 square yards of polymer-modified chip seal surface is placed on approximately 30 miles of streets and parking lots in various locations of the city. The chip sealing process is an efficient and cost effective method of prolonging the useable service life of asphalt pavement. 

Residents and businesses, located along streets being improved, receive a door hanger notice approximately five days in advance of the construction and again 24-hours prior to the work. The City asks that residents remove all vehicles from the streets and avoid releasing water into the street, during the time that they are scheduled for work.

Work is limited to outlying portions of the community until Monday, April 29, 2019, due to the Desert Storm Weekend Event.

Lake Havasu City asks for patience and cooperation during the street sealing process.  Motorists traveling on a street being chip sealed can expect delays and experience access restrictions. Motorists should use alternate routes whenever possible. 

Contact: Maintenance Services Division

Below is a list of the roadways scheduled for the proposed work.

MONDAY - APRIL 15, 2019
STREET FROM/TO
ALIBI DR OAKRIDGE DR to ANITA AVE
ATLANTIC DR AVALON AVE to AVALON AVE
ATLANTIC DR NEPTUNE DR to AVALON AVE
AVALON AVE LAKE HAVASU AVE to ANITA AVE
FISHERMAN DR PRIVATEER DR to CATAMARAN DR
FLAGSHIP DR ATLANTIC DR to RIVERBELLE DR
INVERNESS DR PALO VERDE BLVD to AVALON AVE
INVERNESS DR DANIEL DR to GLENGARRY DR
INVERNESS DR AVALON AVE to DANIEL DR
OAKRIDGE DR W END to APPLE TREE DR
OUTRIGGER DR AVALON AVE to LAKE HAVASU AVE
PEBBLE DR ANITA AVE to AVALON AVE
PRIVATEER DR AVALON AVE to CATAMARAN DR
RIVERBELLE DR ATLANTIC DR to MALAHINI DR
WEDNESDAY - APRIL 17, 2019
STREET FROM/TO
ALIBI DR ANITA AVE to BENTLEY BLVD
ALLEY 3 BENTLEY BLVD to MILAN DR
APPLETREE DR BENTLEY BLVD to
APPLETREE DR EAST END to BENTLEY BLVD
CLOVER LAWN DR SANDWOOD DR to CATALINA DR
CORRAL DR ALIBI DR to OAKRIDGE DR
CURTIS DR MILAN DR to BENTLEY BLVD
JANET DR BENTLEY BLVD to NORRIS DR
MILAN DR CURTIS DR to PALO VERDE BLVD
MILAN CT MILAN DR to CUL DE SAC
NORRIS DR N END to JANET DR
PALISADES DR CATALINA DR to AVALON AVE
PALISADES CT PALISADES DR to CUL DE SAC
SIMITAN DR ARABIAN DR to DESERT VIEW DR
THURSDAY - APRIL 18, 2019
STREET FROM/TO
ARABIAN DR SIMITAN DR to DESERT VIEW DR
CALIENTE DR IRONWOOD DR to LEAWOOD DR
CRESTVIEW DR MAVERICK DR to RUSTLER DR
DESERT VIEW DR KIOWA BLVD to SIMITAN DR
HIDDEN VALLEY DR PALO VERDE BLVD to BRIARCREST DR
HIDDEN VALLEY DR 3279 HIDDEN VALLEY DR to RUSTLER DR
PENNY DR CLIFFWOOD DR to ASCOT DR
SILVERADO DR RUSTLER DR to CRESTVIEW DR
SOMBRERO DR SAND DAB DR to DESERT VIEW DR
SOMBRERO DR PALO VERDE BLVD to SAND DAB DR
SUNKEN TREE DR EMPRESS DR to BEVERLY GLEN DR
FRIDAY - APRIL 19, 2019
STREET FROM/TO
CATTAIL DR YONDER DR to MISSION DR
CISCO DR N SMOKETREE AVE to EL DORADO AVE
CRESTWIND DR IROQUOIS DR to MAVERICK DR
EL TORO DR TARPON DR to JAMAICA BLVD
PELICAN DR TARPON DR to SWORDFISH DR
SWORDFISH DR JAMAICA BLVD to MCCULLOCH BLVD
TARPON DR MCCULLOCH BLVD to INDIAN PEAK DR
YONDER DR MCCULLOCH BLVD to TARPON DR
SATURDAY - APRIL 20, 2019
STREET FROM/TO
BRIAR WAY TARPON DR to MISSION DR
CHERRY TREE DR MCCULLOCH BLVD to MISSION DR
CHIRICAHUA DR PRINCESS DR to BUENA VISTA AVEUNE
FREMONT DR CATARACT DR to ACOMA BLVD
MISSION DR MCCULLOCH BLVD to CHESAPEAKE BLVD
MISSION WAY MISSION DR S to SLOOP DR
MOCCASIN DR THUNDERBOLT AVE to ROLLING HILLS DR
PASO DR ACOMA BLVD to FREMONT DR
SLOOP DR MCCULLOCH BLVD to CHESAPEAKE BLVD
TALISMAN DR VIEJO DR to VIEJO DR
NO WORK SCHEDULED FOR WEEK OF APRIL 22-26
PROJECT WILL RESUME ON MONDAY (APRIL 29)
SUBSCRIBE TO NEWS & UPDATES

We will send you email alerts when the city releases a news article.

*Required